The purpose of the blog post is to explain the Order change management functionalities of SAP.

The general concept of the OCM is to be able to handle the critical changes which happen between the production start and the delivery date. Before the production start, changes can be controlled through change master, ECR-ECO/Engineering record, and by re-reading master data in production order.

In this blog post, I will show one end-to-end scenario where a BOM com component gets deleted in the production order after the production start. In the next series of blog posts, I will detail the configuration and a few more scenarios.

I am not detailing the configuration in the first blog. You need to have an overall profile (Configured in OPL9) which groups change profile for sales and production orders changes. This overall profile should be assigned to the material master in the work scheduling view.



74_2.png


Now check the production order for the material in mD04

74_3.png




Scenario:

We will delete a component from the BOM and check if it is updated in the production order using OCM.

Production order – Component 13352 would need to be deleted through the OCM process.

74_4.png


Create a Change master in CC01 with an effectivity date. The changes to the order BOM would be effective from that day.

74_3.jpg


Change the BOM using this EC – CS02. Delete the component 13352

74_5.png


The engineer makes the changes in the BOM and releases the change master.

74_6.png


Order Change Management

T-Code: COCM

Menu Path: SAP MENU > LOGISTICS>PRODUCTION>PRODUCTION CONTROL>CONTROL>ORDER CHANGE MANAGEMENT> CHANGE PROCESS>INITIATING OBJECT RECORDS

74_4.jpg


Click on the EC number and hit Execute (search for procurement elements). This may take a few seconds to pull up.

Expand the Change Number, Click on the production order, and Hit Process Procurement Element.

74_5.jpg


In the next screen, select the Order and Hit Execute. In the popup, select all three and hit Continue – the green check mark.

74_7.png


After it completes, the columns show what functions have been completed.

74_8.png


The production order is updated with the new BOM. The material 13352 is removed from the BOM.

74_9.png


You can check what changes were made by clicking on the Changes button. You can see Type as “-,” which means deletion.

74_10.png


Now the natural question would be how SAP decided under which circumstances it deleted the component? Because the order may be under different status (Operation/component/header). This is what will be explained in in next blog post.

Please provide feedback to share more such blog posts.