SAP BLOG S/4HANA MRP – to Live or not to Live: Planned orders numbering

SAP Blog

Kayıtlı Üye
Katılım
22 Ara 2017
Mesajlar
1,925
Tepki puanı
7
Puanları
6
MRP Live deletes all planned orders and recreates them with each planning run.

Show piece of source code, maybe a note on that.

Refer to note that recommends rescheduling of planned orders, not regenerative planning.

Show standard configuration of planned order number ranges.

Point out risk of running out of numbers. Especially that MRP Live planes in total horizon, thus creates more planned orders than classic MRP

Okumaya devam et...
 